Reference Number NIA_SGN0117
Title Bolt Integrity
Status Completed
Energy Categories Fossil Fuels: Oil Gas and Coal(Oil and Gas, Refining, transport and storage of oil and gas) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Mechanical, Aeronautical and Manufacturing Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
SGN
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 January 2018
End Date 01 June 2019
Duration ENA months
Total Grant Value £108,153
Industrial Sectors Energy
Region South East
Programme Network Innovation Allowance
 
Investigators Principal Investigator Project Contact , SGN (100.000%)
  Industrial Collaborator Project Contact , SGN (0.000%)
Web Site https://smarter.energynetworks.org/projects/NIA_SGN0117
Objectives The project consists: Complete offsite trials and onsite live trails of the reinforcement clamp. Complete SGN/PM/G23 for reinforcement clamp. Removal of stud bolts using reinforcement clamp on live site. Complete a variety of offsite testing to calculate the corroded cross sectional area and the remaining strength of the stud bolts. Development of a screening tool documenting evidence from offsite testing. This will be developed into a user guide based on bolt conditions, operating parameters and all other relevant details. Development of a bolt replacement procedure and training instructions. Submission of a final project report with full details of the work and testing done throughout the project. The aim of this project is to carry out investigation to develop an understanding of how corrosion affects the strength of a stud bolt and to see if it can be approximated by the cross-sectional area of the uncorroded material. In order to determine the replacement extension for bolt within plants and pipelines, a screening tool will identify the high risk bolts to replace. To do this, specimens will be removed from site using the Hydratight Reinforcement Clamp, and will be subjected to various tests. These tests will determine the remaining strength left in a corroded bolt and cross referenced to understand if there is a visible trend. The objectives of this project are to: Complete offsite trials and onsite live trails of the reinforcement clamp. Complete a variety of offsite testing to calculate the corroded cross sectional area and the remaining strength of the stud bolts. To give a quantitative measure for the corrosion as a percentage of metal loss or cross sectional area. Development of a screening tool documenting evidence from offsite testing. This will be developed into a user guide based on bolt conditions, operating parameters and all other relevant details.Understand how the corrosion affects the remnant strength and life in the bolt. Develop a bolt replacement procedure and training instructions.
Abstract SGN NIA project to inspect bolt condition and trial reinforcement clamp.
Publications (none)
Final Report (none)
Added to Database 02/12/22